Indicative delivery times for bushings and tap-changers

This information is available for tap-changers and bushings from our different production sites: Ludvika, Sweden, Zurich, Switzerland, Hefei, China, and Alamo, Tennessee, USA.

Standard delivery times from Ludvika, Sweden.

The delivery times below reflect our general load situation. However, we reserve ourselves for large orders received during the period in between, which might affect actual delivery time. 

Shorter delivery times are also available but are subject to material availability. Please contact our Sales Department if the indicated delivery times do not meet your requirements and material availability. 

Please note that final delivery times are always as per the order acknowledgment.

Present Preliminary Delivery Times (Updated as of December 19, 2024)

TAP-CHANGERS
UB 14 weeks
UZ 21 weeks
UCG 27 weeks
UCL 27 weeks
UCC/UCD on request
VUBB 14 weeks
VUCG 27 weeks
VUCL 27 weeks
BUSHINGS  
GOB 32 weeks
GOB+ 40 weeks
GOB 1050 34 weeks
GOE ≤1675 34 weeks
GOE 1800 34 weeks
GOE ≤2550 on request
GOE 2600 on request
GOE(2) ≤1425 34 weeks
GOE(2) 1675 34 weeks
GOEK on request
GOM 34 weeks
GOH 14 weeks
GSA-OA/ARF AF/ED ≤170 38 weeks
GSA-OA/ARF AF/ED 245 38 weeks
GSA-OO 38 weeks
GSB 245 37 weeks
GSB 362 37 weeks
GSB 420 37 weeks
GSB 550 on request
GSB 800 38 weeks
GSBK 36 weeks
ARF 245 36 weeks
ARF 300 36 weeks
ARF 362 36 weeks
ARF 420 38 weeks
ARF 550 on request