Indicative delivery times for bushings and tap-changers

This information is available for tap-changers and bushings from our different production sites: Ludvika, Sweden, Zurich, Switzerland, Hefei, China, and Alamo, Tennessee, USA.

Standard delivery times from Ludvika, Sweden.

The delivery times below reflect our general load situation. However, we reserve ourselves for large orders received during the period in between, which might affect actual delivery time. 

Shorter delivery times are also available but are subject to material availability. Please contact our Sales Department if the indicated delivery times do not meet your requirements and material availability. 

Please note that final delivery times are always as per the order acknowledgment.

Present Preliminary Delivery Times (Updated as of June 20, 2024)

TAP CHANGERS
UB.. 16 weeks 
UZ.. 22 weeks     
UCG.. 20 weeks        
UCL.. 20 weeks          
UCC../UCD... 20 weeks    
VUBB.. 16 weeks       
VUCG.. 20 weeks          
VUCL.. 20 weeks
BUSHINGS
GOB 34 weeks
GOB+ 40 weeks
GOB 1050 39 weeks
GOE ≤ 1675 39 weeks
GOE 1800 39 weeks
GOE ≤ 2550 On request 
GOE 2600 On request
GOE(2) ≤ 1425 39 weeks
GOE(2) 1675 39 weeks
GOEK On request
GOM 39 weeks
GOH 20 weeks 
GSA-OA/ARF AF/ED ≤ 170 36 weeks 
GSA-OA/ARF AF/ED 245 36 weeks 
GSA-OO  36 weeks 
GSB 245 33 weeks
GSB 362 33 weeks 
GSB 420 33 weeks 
GSB 550 On request
GSB 800 37 weeks
GSBK 33 weeks
ARF 245 33 weeks
ARF 300          33 weeks
ARF 362          39 weeks
ARF 420          On request
ARF 550         
On request